$34bn and counting – beware cost overruns in an era of megaprojects

  • Written by: Greg Moran, Senior Associate, Grattan Institute

A Grattan Institute report[1] released today finds Australian governments spent A$34 billion, or 21%, more on transport projects completed since 2001 than they first told taxpayers they would. And as we enter the era of megaprojects in Australia, costs continue to blow out.

Transport projects worth A$5 billion or more in today’s money were almost unheard of ten years ago. Today, as the chart below shows, megaprojects make up the bulk of the work under way across the country.

$34bn and counting – beware cost overruns in an era of megaprojects Author provided These megaprojects include WestConnex[2] in Sydney, West Gate Tunnel[3] in Melbourne and Cross River Rail[4] in Brisbane. And this is to say nothing of some enormous projects being planned, such as Melbourne’s Suburban Rail Loop[5]. We are also hearing calls to add to this bulging pipeline. In June, the transport and infrastructure ministers of all states and territories said[6] they were “clearing the way for an infrastructure-led recovery” from the COVID-19 recession. Read more: We may live to regret open-slather construction stimulus[7] Cost overrun risks rise with project size The Grattan report, The rise of megaprojects: counting the costs[8], sounds a warning about the risks of this approach. The report uses the Deloitte Access Economics Investment Monitor[9] to look at the final cost of all public road and rail projects worth A$20 million or more and completed since 2001. As the chart below shows, we found bigger projects overran their initial cost estimates more often and by more. $34bn and counting – beware cost overruns in an era of megaprojects Author provided Almost half of the projects with an initial price tag of more than A$1 billion in today’s money had a cost overrun. These projects overran their initial costs by 30% on average. The extra amount spent on some megaprojects was the size of a megaproject itself. Cost announcements before governments were prepared to commit formally to a project were particularly risky. Only one-third of projects had costs announced prematurely, but these accounted for more than three-quarters of the A$34 billion overrun. Read more: Missing evidence base for big calls on infrastructure costs us all[10] When early costings of infrastructure turn out to be too low, it distorts investment planning in three ways: underestimating the costs of transport infrastructure can lead to over-investing in it relative to other spending priorities if governments misunderstand the uncertainty in a project’s cost at the time they commit to it, their decision to invest in that project was made on an incorrect basis because unrealistic cost estimates are more prevalent for larger projects, governments are more likely to over-invest in larger projects. There’s also a fourth and no less important problem: when unrealistically low cost estimates are announced, the public is misled. Despite the experience of the past 20 years, the costs of big projects continue to be underestimated. The chart below shows A$24 billion more than first expected will be spent on just six mega megaprojects (that is, projects with an initial cost estimate of A$5 billion or more) now under construction. Overruns on other megaprojects have been reported[11] too. $34bn and counting – beware cost overruns in an era of megaprojects Author provided Read more: Transport promises for election 2019: the good, the bad and the downright ugly[12] What needs to be done? With megaproject costs continuing to blow out, governments should take immediate steps to manage better the portfolio of work under way — particularly if they are looking to add to it in the name of economic stimulus. Each state’s auditor-general should conduct a stocktake of current projects. This would give the public and the government a clear picture of the situation. Minister speaking in parliament Ministers should report to parliament any changes in project costs, dates and benefits as they become known. James Ross/AAP Ministers should begin reporting to parliament on a continuous disclosure basis. Any material changes in expected costs, benefits or completion dates of very large projects should be disclosed. Steps should be taken to put decisions on the incoming batch of projects on a sounder basis, too. When announcing a cost, ministers and government agencies should disclose how advanced the estimate is. If the proposal is at an early stage, they should quote a range of estimates. Governments should also require their infrastructure advisory bodies to at least assess — if not approve — large proposals before funding is committed. Looking further ahead, action is needed to stop the pattern of spending billions more than expected on megaprojects. State departments of transport and infrastructure should devote more resources to identifying modest-sized transport infrastructure proposals. Read more: The PM wants to fast-track mega-projects for pandemic recovery. Here's why that’s a bad idea[13] And governments need to start learning from the past. Detailed project data, particularly on expected and actual costs, should be centrally collated in each state. Post-completion reviews should be mandatory on all large projects. These reviews should be published. If there is no change in the way infrastructure is conceived and delivered in Australia, then the era of the megaproject will indeed mean megaproblems.

References

  1. ^ Grattan Institute report (grattan.edu.au)
  2. ^ WestConnex (www.westconnex.com.au)
  3. ^ West Gate Tunnel (westgatetunnelproject.vic.gov.au)
  4. ^ Cross River Rail (crossriverrail.qld.gov.au)
  5. ^ Suburban Rail Loop (suburbanrailloop.vic.gov.au)
  6. ^ said (www.transportinfrastructurecouncil.gov.au)
  7. ^ We may live to regret open-slather construction stimulus (theconversation.com)
  8. ^ The rise of megaprojects: counting the costs (grattan.edu.au)
  9. ^ Deloitte Access Economics Investment Monitor (www2.deloitte.com)
  10. ^ Missing evidence base for big calls on infrastructure costs us all (theconversation.com)
  11. ^ reported (www.theage.com.au)
  12. ^ Transport promises for election 2019: the good, the bad and the downright ugly (theconversation.com)
  13. ^ The PM wants to fast-track mega-projects for pandemic recovery. Here's why that’s a bad idea (theconversation.com)

Authors: Greg Moran, Senior Associate, Grattan Institute

Read more https://theconversation.com/34bn-and-counting-beware-cost-overruns-in-an-era-of-megaprojects-149149

The Weekend Times Magazine

Unique and Trendy Christmas Gift Ideas for 2025 - Best Holiday Gifts Guide

?? Discover unique and trendy Christmas gift ideas for 2025! Your ultimate guide to the best holiday gifts is here! ?? The Importance of the Holiday Season The holiday season is a...

Making these five clever moving mistakes will cost you both money and time

Moving to a new location can be a thrilling adventure, but it can also be costly and stressful. Because so much packing, planning, and logistics are involved, it is easy...

Tips for Choosing a Caravan for Australian Conditions

Australia's landscapes are unlike anywhere else in the world. From scorching outback heat and corrugated dirt tracks to coastal humidity and alpine cold, the demands placed on a caravan can...

Why More Buyers Are Choosing Lab Grown Diamonds Brisbane and Lab Grown Diamonds NZ

The popularity of lab-created diamonds has increased rapidly over the last few years, changing the way people shop for fine jewellery. Whether you're searching for an engagement ring, a wedding...

A Great Weekend Shopping Trip Isn't Just About Buying Things

Weekend shopping has changed. For many Australians, a Saturday outing was once built around visiting department stores, browsing specialty retailers and enjoying lunch at a nearby café. Today, many routine purchases happen...

Kmart at home: Why Australians keep coming back for stylish living at everyday prices

There was a time when discount department stores were often associated with buying the basics. A kettle, a mop or a few household necessities would do the job, but style...

5 Ways to Make Maths Fun

For many students, maths can seem like a daunting subject, but with the right approach, it can become one of the most enjoyable and rewarding parts of learning. Whether you’re...

The Importance of Quality Paint Protection for Brisbane Drivers

Shielding Your Vehicle with the Right Protection Every car owner appreciates that fresh showroom finish—the gleam of the paintwork, the smoothness of brand new panels. But once you drive out of...

When Your Perth Pool Needs More Than Maintenance: A Guide to Pool Renovation and Resurfacing

Every pool surface has a finite life. The fibreglass gel coat of a fibreglass pool, the pebblecrete or render of a concrete pool, the vinyl liner of a vinyl pool:...